‘New KIA metro line defeats purpose of public consultation’

As the Metro line towards the airport gets finalized, questions persist on whether the public’s opinion was really given its due.

Bengaluru Development Minister K.J. George recently confirmed that the line to Kempegowda International Airport will start at Nagawara, which is one of the terminal points in Phase II, and head via Thanisandra Road towards Hegde Nagar before taking a turn at Jakkur towards Yelahanka. From Yelahanka, the line will go along the existing airport road. Bangalore Metro Rail Corporation Limited (BMRCL) hopes to use the land abutting the service lanes to reduce land acquisition cost and demolition of existing structures. The line will extend Phase II of Metro by nearly 28km.

However, this alignment was not among the nine routes that BMRCL had put forth before the public in September 2016 for suggestions and feedback. Over 1,000 responses had been received.

The alignment is a mixture of two options: Nagawara-Kogilu Cross-Yelahanka-airport and Nagawara-Bellahalli-Yelahanka.

“This option was not mentioned during the consultations. The purpose of public consultation has been defeated,” said Sanjeev V. Dyamannavar, a member of Praja RAAG, a collective that has been advocating public transportation for decongesting Bengaluru.

He believes that the alignment will lead to a host of challenges, including traversing Jakkur aerodrome and Yelahanka air base. “The elevated sections will run into problems in front of these airports. It will effectively kill Jakkur training school while the air force will not accept an elevated section right beside its runway. Moreover, the sharp turns at Hegde Nagar and Yelahanka will curtail the speed of the train,” he said.

Pradeep Singh Kharola, Managing Director of BMRCL, said this route was chosen to cater to the high-density residential neighborhoods of Hegde Nagar and Yelahanka. “The inputs given by the public did play a role in the decision-making. A huge amount of analysis that has gone into the decision,” he said.

With work on the Detailed Project Report starting right away, he said the ‘challenges’, including approvals from the air base and the aerodrome, will be discussed over the course of planning and execution.

Is there too much on BMRCL’s plate?

Phase II and its addendum, including lines to the airport and the Outer Ring Road line from K.R. Puram to Silk Board junction, now span 119 km, which is nearly 2.5 times that of Phase I.

Currently, BMRCL is juggling nine reaches of Phase II; work orders have already been given in seven lines. Bids have been invited or tenders are yet to be finalized in two lines. This does not include the massive 13.7-km underground section from Dairy Circle to Nagawara, which officials said will be done through numerous tenders while the financial planning of the ORR and airport lines are yet to gather perceptible steam.

“They have their hands in too many places now without the capacity or funds in hand,” said Sanjeev V. Dyamannavar, a member of the non-government organization Praja RAAG. He believed BMRCL is tackling the ‘easy reaches’ on Mysuru, Kanakapura and Tumakuru roads but is bogged down on ‘crucial lines’. “Groundwork has not been carried out on key lines. Work on the Gottigere to Nagawara underground line and the crucial Baiyappanhalli to Whitefield lines are yet to start. Even the design of the interchange station on the line to Electronic City has not been fixed. These will lead to cost escalation.”

He believes the problems of Phase I will persist, particularly manpower required to execute the complicated connectivity. “There are hardly any people with a railways background in BMRCL. Delhi Metro has done well because a lot of people from Indian Railways were deployed there,” he explained.

Ashish Varma from the Centre for infrastructure, Sustainable Transportation, and Urban Planning at the Indian Institute of Science hoped that the experience gained during construction of Metro Phase I will lead to the faster execution of Phase II.

The popular blog, The Metro Rail Guy, estimates that BMRCL managed to construct and commission 3.03km of metro rail every year.

“This is always going to be a challenge, and they should see if their institutional capability will lead to better execution. The hope is that they will better use GIS (Global Information System) to plan the lines and have better stakeholder discussions,” said Mr. Varma referring to the problems in land acquisition and tree cutting permissions.

Pradeep Singh Kharola, Managing Director of BMRCL, however, is confident. “We have learnt from Phase I and the manpower is there. This is a much bigger project and we are capable of handling it,” he said.

Newsletter

AJK College Hosts Workshop on Building Resilient Systems

The Department of Computer Science with Data Analytics at AJK College of Arts and Science conducted a workshop on "Build...

Construction worker sentenced to 20 years rigorous imprisonment for sexually assaulting 9-year-old girl

A 50-year-old construction worker from Kangeyam, Tirupur district, was sentenced to 20 years of rigorous imprisonment fo...

Bomb Threat Email Sent to Coimbatore International Airport, Confirmed as Hoax

An unknown person sent a bomb threat email to Coimbatore International Airport on Tuesday night. CISF's Bomb Detection a...

EASA College Student Wins First Place in Tamil Oratory Competition

G. Santhapandi, a second-year ECE student from EASA College of Engineering and Technology, Coimbatore, secured first pla...

Farmers Protest Against Substation and High-Tension Tower Projects Near Tirupur

Over 100 farmers and villagers staged a demonstration in front of the District Collector's office in Tirupur, demanding...

Millions of Liters of Water Wasted as Tirupur's Fourth Joint Drinking Water Scheme Pipeline Bursts

A burst pipeline in Tirupur's Fourth Joint Drinking Water Scheme has been wasting millions of liters of water for three...