Our waste will fuel cement factories

Within two months, a mammoth 13 lakh kilogrammes of waste that has been processed as fuel, will be lifted from the overburdened six recycling plants in the city.

At a recent meeting with cement industries and civic officials, Karnataka State Pollution Control Board (KSPCB) negotiated the removal of accrued Refuse Derived Fuel (RDF) within two months.

In the plants, inorganic waste - primarily plastic - is shredded, crushed and moisture entirely removed to form RDF, which can be used as fuel in the incineration plants of cement factories. Since the project started, over 18 lakh kilogrammes of RDF has been manufactured, of which just 5 lakh kg have been taken by cement plants.

Though the fuel is being given for free, for the cement plants, the high transportation costs had become a major hindrance. Much of the factories are in north Karnataka, at a distance of over 500 km. The cost of transportation came up to Rs. 2,500 per tonne.

The estimate for removal of the accumulated RDF comes up to more than Rs. 3.25 crore. “As a temporary measure, we have asked the cement factories to use their Corporate Social Responsibility (CSR) funds to lift the waste. But, in the long term, we will work with the BBMP to bring out a policy to sort out this issue,” said Lakshman, Chairperson, KSPCB.

The accumulation of RDF in processing plants has already resulted in two major fires — at the Kannahalli plant in October and at the Chikkanagamangala plant in November.

Policy for RDF

“Once this accumulated RDF is cleared, we will look at evolving a viable model for dealing with the produced fuel,” said Sarfaraz Khan, Joint Commissioner (Solid Waste Management), BBMP. The model could involve BBMP seeking State government support to subsidise the transportation cost by more than 50 percent.

What is RDF

Outcome of crushing inorganic waste (plastic) and removing moisture
Calorific value: 1,500 kilo calories per kg
Can be incinerated by using just 5 percent fuel

Production

Six waste processing plants can produce up to 1,350 tonnes of RDF per day
18,147 tonnes of RDF produced so far
Just 5,126 tonnes have been lifted by two cement companies so far

The problem

Cement factories are in north Karnataka
Transportation costs: Rs. 2,500 per tonne
Cost is not viable for factories

Solution

Cement companies asked to utilise CSR funds temporarily
BBMP to devise means to subsidise transportation cost

Evening Thunderstorms Likely Across Coimbatore Over Next 3 Days

Coimbatore to experience hot mornings and increasing evening thunderstorm activity over the next three days, with clouds...

Coimbatore Press Club flags irregularities in issuing media passes for covering election counting

Coimbatore Press Club has alleged discrepancies in issuance of media passes for polling and counting, urging the Chief E...

“Not 140 — Over 200 Seats Certain,” Says Selvaperunthagai in Coimbatore

Speaking at Coimbatore Airport, Tamil Nadu Congress leader Selvaperunthagai dismissed opinion polls as attempts to “shap...

Youth dies after car plunges into roadside pond near Periyanaickenpalayam

A youth died after his car plunged into a roadside pond on Kattanji Malai–Thayanur road near Periyanaickenpalayam in Coi...

DYFI Protests in Coimbatore Against Railway Staff Reduction, Says PM’s Promises Not Fulfilled

Members of the Democratic Youth Federation of India (DYFI) staged a protest in front of Coimbatore Railway Station again...

Coimbatore City Police Announce Traffic Diversions for This Evening’s Flag March Ahead of Vote Counting

Traffic restrictions will be in place across key stretches in Coimbatore this evening (May 2) as city police conduct a f...